Cenovus West White Rose Project
Provided engineering and site management support at the Bull Arm Fabrication Site in preparation for critical West White Rose Project marine operations
Cenovus West White Rose Project
- Provided engineering and site management support at the Bull Arm Fabrication Site in preparation for critical West White Rose Project marine operations
- Supported readiness for the arrival of the COSCO Heavy Transport Vessel Xin Yao Hua carrying the WWRP Topsides from Ingleside, Texas
- Developed detailed mooring and securing plans to safely berth the heavy transport vessel at the Bull Arm pier
- Defined technical requirements and procedures for the safe removal of sea-fastenings from the Load-Out Support Frame
- Supported the transfer of the Topsides from the COSCO vessel to Allseas’ Pioneering Spirit installation vessel
- Prepared for and supported the arrival of the Pioneering Spirit, including discharge of the Single Lift Platform (SLP)
- Developed safe relocation strategies and work sequences to move the SLP to a designated dismantling area and support its demobilization
- Contributed to the safe execution of complex marine operations, heavy-lift interfaces, and on-site logistics, supporting Cenovus’ offshore installation readiness